The 2020 WA strata reforms made reserve funds and 10 year plans compulsory for designated strata companies: schemes with 10 or more lots, plus certain smaller schemes where the relevant building or common property replacement cost exceeds $5 million. For many existing schemes, the first required plan was approved in 2021 or 2022. The Act requires each plan to be revised at least once every five years, so those plans are now reaching their first revision point.
That timing matters for another reason. The construction market those plans were priced against looks very different today.
What Has Happened to Costs Since the First Plans
The Australian Bureau of Statistics tracks the prices builders receive for different types of construction work. Its index for other residential building construction in Western Australia covers apartments, flats and other residential buildings except freestanding houses, including alterations and renovations. That index rose 35.3% between June 2021 and June 2026, including 6.0% in the latest 12 months.
Rider Levett Bucknall’s September quarter 2026 update describes the WA construction sector as running at or near peak capacity across defence, healthcare, renewable energy, manufacturing and residential work. RLB has raised its forecast for Perth tender prices to 6.5% in 2026, and expects a further 5.9% in 2027.
The ABS index is not a measure of strata maintenance and is no substitute for project specific pricing. It provides useful context for the broader residential construction pricing pressures relevant to many strata capital works.
Check the Assumptions Written Into Your Plan
The Strata Titles (General) Regulations 2019 require every 10 year plan to state “the method by which the estimated costs … were determined, including any assumptions underlying that determination” (regulation 77(1)(g)). The basis for the cost estimates should be written into the plan, so it is a good place to start.
If a plan allowed 3% a year for escalation, it built in a 15.9% increase over five years. The ABS index for other residential building construction in WA rose 35.3% over the same period, more than twice as much.
Consider an illustrative example. A 24 lot scheme’s 10 year plan, prepared in mid 2021, priced a roof replacement at $300,000 in 2021 dollars and allowed 3% a year for escalation.
- What the plan expects the job to cost in 2026: about $348,000
- Illustrative 2026 cost if the item had moved in line with the ABS index: about $406,000
- The gap: about $58,000, or roughly $2,400 per lot if shared equally
Actual contributions follow unit entitlements, and every job is different. A gap can arise even where the assumptions in the original plan were reasonable at the time.
What could another year of price growth mean? RLB currently forecasts Perth tender prices to rise 5.9% in 2027. As a simple scenario, a 5.9% increase on a $406,000 project is about $24,000. That is not a forecast for this roof or any particular project, and actual costs may move differently. Whether waiting or financing costs less overall will depend on the project, the timing and the cost of finance.
Landgate Is Also Reviewing How 10 Year Plans Are Working
Landgate is administering the statutory five year review of the Strata Titles Act 1985. Its phase one discussion paper, released for consultation in October 2024, reported feedback that the 10 year plan requirement “may not be operating as intended”.
The paper notes that the Act requires a strata company’s budget to take the 10 year plan into account, but says “this is not always resulting in an adequate budget allocation to cover future maintenance”. It raised the possibility of an obligation to fund the plan, as already applies in New South Wales.
It also points out that more than 30% of WA strata schemes are over 31 years old, and that for ageing buildings “contributions may not be able to be raised to fund critical building safety work”.
As at October 2026, phase two of the review, where possible reforms will be released for public comment, has not been published. Whatever phase two proposes, the existing five year revision requirement continues to apply.
What to Do Across Your Portfolio
- Find the plans that are due. Check any plan approved or last revised in 2021 now. Depending on its approval date, its five year revision point may already have passed. Plans approved in 2022 reach that point during 2027.
- Read the cost assumptions. Compare the escalation allowance in each plan against what has actually happened. If a plan allowed 2 to 3% a year, flag the major near term items for closer review.
- Rank by exposure. Put schemes with large items due in the next three years at the top: roofs, lifts, balconies and balustrades, waterproofing, façades and fire services.
- Ask how the estimates will be refreshed. Talk to the plan provider about the large items due in the next few years, and whether they should be repriced using current market evidence rather than carried forward on the original escalation assumption.
- Start early enough for the AGM. The budget put to the AGM must take the 10 year plan into account. Commission the revision early enough for the council to review it before the AGM papers and budget are finalised.
- Look for work that can be bundled. Combining works that share scaffolding, access or contractor mobilisation can avoid paying for those costs twice.